EXECUTIVE
SUMMARY
1. This report
provides an update on progress against the Panel’s work plan.
EXEMPT INFORMATION
2. Not exempt
3. The Panel is asked to:
i. Comment on the revised work plan
detailed in Appendix A.
ii. Note the Annex to Appendix A which
details outcomes and impacts of the Panel’s work.
iii. Receive an update on activities
undertaken since the meeting held on 19th November 2012.
iv. Note
the correspondence between the Executive and the Regeneration and Environment
Overview and Scrutiny Panel in Appendix B and C regarding Work, Skills
and Enterprise Programme Going Forward and Update on Opportunity Centres.
v. Note the minutes on the joint review
being undertaken by Members from the Regeneration and Environment and Schools,
Children and Young People ‘To Understand And Address Careers Advice And
Guidance To Children And Young People Within Doncaster Pre And Post 16’ attached in Appendix D and E.
vi. Note the action
points for the last Enterprising Doncaster meeting that was held on the 29th
October 2012 in Appendix F.
vii. Note the
Qtr. 2 2012-2013 Performance Report as circulated to Members of the
Regeneration and Environment Overview and Scrutiny Panel in Appendix G.
4. The Panel agreed its 2012/13 work plan at
its meeting on 15th June 2012. This report provides an update on key
issues relating to the work programme following that meeting, this is attached
at Appendix A. Members are reminded that the work plan is a live document to be
regularly reviewed and updated. Annex 1 to Appendix A provides an ongoing summary of issues considered together with the
impacts and outcomes resulting from the Panel’s work and this will also be
updated on a regular basis.
Progress on
the Regeneration and Environment Overview and Scrutiny Work Plan
Careers
and Guidance Review - ‘To Understand and
Address Careers Advice and Guidance to Children and Young People within Doncaster
Pre and Post 16’
5. In
respect of the Careers and Guidance review, a joint working group was formed with Members from the Regeneration and
Environment and Schools, Children and Young People Overview and Scrutiny Panel. Members from the working group attended
a series of meetings on the 6th and 11th December 2012 to
look at a range of information. The
group firstly met with Members of the Youth Council on the 6th
December 2012 then with representatives from the Work and Enterprise Board and
partnership organisations on the 11th December 2012. The notes from those meetings have been
attached in Appendix D and E and the Chair of the group, Councillor Richard
Cooper-Holmes will feedback at the Panel’s meeting itself. Following the meeting, it was decided that a
further meeting will be arranged in February 2013, to find out more about what schools are
doing, will look at the role of the school governor and receive further feedback
from the Work and Schools Board.
OPTIONS CONSIDERED
6. There are no specific
options to consider within this report as it provides an opportunity for the
Panel to receive an update on its 2012/13 work plan.
REASONS FOR RECOMMENDED
OPTION
IMPACT ON COUNCIL’S KEY OBJECTIVES
Priority
Theme |
Mayor’s
Priorities for 2011/12 |
Implications
of this initiative |
1. Creating a strong, connected and inclusive
economy
|
· Drive
forward the Doncaster economy · Get the
balance of public and private transport right · Promote
Doncaster as a tourist destination · Regenerate
Doncaster's town centres |
The
Overview and Scrutiny function has the potential to impact upon all of the
council’s key objectives by holding decision makers to account, reviewing
performance and developing policy through robust recommendations, monitoring
performance of council and external partners services and reviewing issues
outside the remit of the council that have an impact on the residents of the
borough. |
2.
Developing stronger communities |
· Encourage
community harmony and cohesion. Treat people as individuals, not by
reference to labels and artificial groupings |
|
3. Increasing and improving housing |
· Raise
housing standards |
|
4. Protecting and improving all our children’s
lives |
· Continue
to improve education and skills · Build on a
strengthening Children's Service |
|
5. Improving health and support for independent
lives |
· Encourage
attitudes of self-reliance, self-improvement and mutual respect within
Doncaster communities |
|
6.
Tackling crime and anti-social behaviour |
· Reduce
crime and all forms of anti-social behaviour |
|
7.
Creating a cleaner and better environment |
· Continue
to protect the environment from developers, decay and architectural vandalism |
|
8.
Internal Transformation |
· Ensure
local people get value for money from council services |
RISKS
AND ASSUMPTIONS
8. To maximise the
effectiveness of the Overview and Scrutiny function it is important that the
work plan devised is manageable and that it accurately reflects the broad range
of issues within its remit. Failure to
achieve this can reduce the overall impact of the function.
LEGAL
IMPLICATIONS
9. The Council’s Constitution states that
subject to matters being referred to it by other parts of the Full Council,
OSMC or the Executive and any timetables laid down by those references the Regeneration
& Environment Overview and Scrutiny Panel will determine its own work
programme (Overview and Scrutiny Procedure Rule 6c).
10. Overview and Scrutiny Panels Terms of Reference
– 3, states that the Panel is empowered to establish ad hoc working groups from
within its membership, to undertake project and policy development work, to
meet the objectives and targets of its annual work plan.
11. Overview and Scrutiny Procedure Rule 15 (a)
states that where, in the opinion of the Chair of an Overview and Scrutiny
Panel, the matters under discussion are relevant to matters referred to other
Scrutiny Panel(s) he/she shall consider to what extent to invite the
participation of the Chair and/or other Members of the other Panel in the
deliberations.
12. Specific legal implications and advice will
be given with any reports when Overview and Scrutiny have received them as
items for consideration.
FINANCIAL
IMPLICATIONS
13. The budget for the support of the Overview
and Scrutiny function 2012/13 is not affected by this report however, the
delivery of the work plan will need to take place within agreed budgets. There are no specific financial implications
arising from the recommendations in this report. Any financial
implications relating to specific reports on the work plan will be included in
those reports.
CONSULTATION
14. A work planning event was held on the 22nd May 2012
with Regeneration and Environment Overview and Scrutiny Members with a view to
developing a draft work plan.
BACKGROUND PAPERS
15. None
CONTACT
OFFICER AND REPORT AUTHOR
Caroline Martin
Scrutiny Officer
01302 734941
caroline.martin@doncaster.gov.uk
Peter Dale
Director of
Regeneration & Environment
.Regeneration and Environment Overview
and Scrutiny Workplan 2012/2013
|
22nd May 2012, 3:30pm |
15th June 2012, 10am |
29th June 2012, 10am |
3rd September 2012, 2pm |
17th October 2012,
10am |
19th November 2012,
10:00am |
22nd January 2013, 10:30am |
18th March 2013, 10am |
Policy Review/ Development |
SMC
Options |
Local
Development Framework - Next Steps |
Gypsy
and Traveller Review |
Work
and Skills |
|
|
Sites and Policies Development Plan Document |
|
|
|
|
|
|
Adoption
of the Doncaster Council Statement of Policy (Gambling Policy 2013) |
|
|
|
Performance |
|
St
Leger Performance 2011/2012 (Qtr 4) |
|
R&E
Performance 2012/13 (Qtr 1) St
Leger Performance 2012/13 (Qtr 1) |
|
St
Leger Performance 2012/13 (Qtr 2) |
|
R&E
Performance 2012/13 (Qtr 3) St
Leger Performance 2012/13 (Qtr 3) |
Information Updates |
|
|
|
|
|
|
|
|
Scrutiny (Holding to Account) |
|
Cabinet
Members Portfolio Updates: - Peter
Davies, Mayor of Doncaster |
|
Cabinet
Members Portfolio Updates: Councillor
C Ransome |
Cabinet
Members Portfolio Updates: - Councillor
P Coddington |
Cabinet
Members Portfolio Updates:- Councillor
B Hoyle |
Cabinet
Members Portfolio Updates: Councillor
Ransome |
Cabinet
Members Portfolio Updates: - Councillor
Hoyle |
Other |
|
|
|
|
Work,
Skills And Enterprise Programme Going Forward And Update On Opportunity
Centres |
|
|
Careers
& Guidance Housing |
|
|
R&E
Workplan 2012/13 |
|
R&E
Workplan 2012/13 |
|
R&E
Workplan 2012/13 |
R&E
Workplan 2012/13 |
R&E
Workplan 2012/13 |
|
May 2012 |
June 2012 |
July 2012 |
August 2012 |
Sept 2012 |
Oct 2012 |
Nov 2012 |
Dec 2012 |
Jan 2013 |
Feb 2013 |
March 2013 |
April 2013 |
Briefing Notes |
|
|
Performance Information – 2011/2012 Quarter 4 |
|
|
|
Performance
Information – 2012/13 Quarter 2 Environmental
Strategy circulated for comment Planning Project
Pipeline |
|
Portfolio
Updates Peter
Davies, Mayor of Doncaster (Briefing) |
|
|
|
Reviews/ Working Groups: - |
|
|
|
Environmental
Strategy Working Group |
Report
to R&E O&S – Work & Skills |
|
Report
to R&E O&S – Environmental Strategy Work
& Skills LMI/Careers
& Guidance Working Group |
Careers
& Guidance Review Meetings |
|
Careers
& Guidance Review Meeting Housing
Review Meeting |
Draft
Report to R&E O&S on Careers & Guidance Review |
|
Members Workshops/ Seminars |
Local Development Framework – Next Steps (PD) |
CCQ
Progress |
|
Key
Principles of Allocations Policy Review |
|
New
Tenancy Strategy Housing
Allocations Follow Up |
|
|
|
|
|
|
Regeneration
& Environment Outcomes and Impacts 2012/13 (January 2013 Update)
DATE |
ISSUE/ OUTCOME |
COMMENT |
WHO |
WHEN |
IMPACT |
22nd May
2012 |
SMC Options Opportunity
for the Panel to consider and comment on a range of options (including a
preferred option) for the future management of the Keepmoat
Stadium. The
Panel supported the preferred option and made further recommendations
including that: - 1.
The Athletics club are encouraged to consider being set
up as a trust and in the event that this was to occur, that Elected Members
are included as representatives on the board of that trust. 2.
That the Chief Executive of Doncaster Rovers attends
meetings of the Regeneration & Environment Overview and Scrutiny to present on a quarterly basis a progress
report including relevant feedback and performance information. |
To understand the
options being taken forward and have the opportunity to comment on them and
make recommendations. |
Panel |
Cabinet
1st August 2012 Quarterly
updates from the Chief Executive of Doncaster Rovers to commence January 2013
subject to availability |
Cabinet agreed the final proposals as outlined in
the report.
The
Chief Executive of Doncaster Rovers to attend meetings of the Panel to
present on a quarterly basis a progress report including relevant feedback
and performance information. |
15th
June 2012 |
Local Development
Framework - Next Steps Opportunity for the panel to consider the proposed approach for consultation on
the sites and policies development plan document/draft process for dealing with neighbourhood planning and
the proposed prioritisation of support for those areas identified within the
core strategy as being suitable for most growth and on-going work to consider
community infrastructure levy. |
To understand the on-going work and proposed consultation and
approaches being taken forward in relation to the LDF. To have the opportunity to comment on the
report and its recommendation and make before a decision is made at Cabinet. |
Panel |
Decision
taken at Cabinet 4th July 2012 |
The
Panels supported the recommendations being put forward to Cabinet and made a
number of comments which were incorporated into the report which included the
proposed approach to consultation.
This included the need to
ensure that communities in the renewal towns were consulted via parish /town
councils (reflected in paragraph 21) and that it was important that members
were aware of the potential housing and employment sites in their wards, in
advance of the public consultation (officers will ensure this happens). |
Cabinet Members
Portfolio Outline: Peter Davies, Mayor of Doncaster Development; Transport; Equalities and Cohesion;
the Council's Change Programme |
To
understand priorities and review progress later in year. During the course of
the year continue to measure aspects through Quarterly Performance reports. |
Panel |
June
2012 meeting and quarterly performance reports Update
early 2013 |
To
provide accountability for improvement and improve transparency. |
|
29th
June 2012, |
Gypsy and Traveller
Review To
comment and note on a report and recommendations considered by Mayor and Cabinet on 4th July in relation to findings of the
gypsy and traveller accommodation needs assessment and the strategy to meet
those needs and the progress of the refurbishment scheme at the gibbons lane
site and the extension scheme at land’s end. |
To be informed about the Gypsy and Traveller Review. To have the opportunity to comment on the
report and its recommendations and make before a decision is made at Cabinet. |
Panel |
Decision
taken at Cabinet 4th July 2012 |
Revised
recommendations were made at Cabinet which took into account comments made by
the R&E O&S Panel. Agreed
at Cabinet that recommendations, following consultation and the cost/benefit
analysis to be brought back to Cabinet for a decision as soon as possible to
enable compliance with the HCA’s timelines.
|
3rd
September 2012 |
Work and Skills
Update Opportunity
to receive information of the private sector led Work & Skills board. |
To receive an annual update on the work of the
Private Sector-led Work & Skills Board in attempting to improve the
Skills our residents have in order to support economic growth across the
Borough. To
consider undertaking a further piece of work around this area. |
Panel |
Cabinet
5th December 2012 |
As part of the recommendations made, the panel
agreed to undertake that a joint working group is formed with members
from the schools, children and young people overview and scrutiny panel
(subject to the agreement of chair of that panel). this group will include members from both
the regeneration & environment and schools, children and young people
overview and scrutiny panel |
Performance 2012/13 (Qtr. 1)- DMBC |
Continue to
monitor. |
Panel |
Through
quarterly report & review |
To
hold relevant Directors and Cabinet Members to account. Focus on key areas of
overspend & underperformance and consider actions for improvement.
Identify issues for future consideration. Ensure
concerns identified continue to be monitored. |
|
Performance 2012/13 (Qtr. 1) – St Leger |
|||||
Cabinet Members
Portfolio Outline: Councillor C
Ransome |
To
understand priorities and review progress later in year. During the course of
the year continue to measure aspects through Quarterly Performance reports. |
Panel |
September
2012 meeting and quarterly performance reports Update
early 2013 |
To
provide accountability for improvement and improve transparency. |
|
17th
October 2012 |
Cabinet Members
Portfolio Outline: Councillor P
Coddington |
To
understand priorities and review progress later in year. During the course of
the year continue to measure aspects through Quarterly Performance reports. |
Panel |
October
2012 meeting and quarterly performance reports Update
early 2013 |
To
provide accountability for improvement and improve transparency. |
Work, skills and enterprise
programme going forward and update on opportunity centres |
To
understand the current position with regard to the future work and skills
support offer within the Work, Skills and Enterprise Programme (Success
Doncaster) and also provides an update on Opportunity Centres. |
Panel |
October
2012 meeting Potential
further updates to be provided on the works, skills and enterprise programme |
Following
a review undertaken as part of the 2011/2012 workplan,
the Panel was brought up-to-date with progress made on recommendations from
the review and the wider picture in terms of the Work, Skills and Enterprise
Programme. Recommendations were made
based on the information presented at the Panel meeting |
|
19th
November 2012 |
Cabinet Members
Portfolio Outline: Councillor B Hoyle |
To
understand priorities and review progress later in year. During the course of
the year continue to measure aspects through Quarterly Performance reports. |
Panel |
November
2012 meeting and quarterly performance reports Update
early 2013 |
To
provide accountability for improvement and improve transparency. |
Adoption of the
first Council Environment Strategy |
As part of the R&E O&S workplan
a working group was set up to look at the Environmental Strategy. |
|
Going
to Cabinet 5th December 2012 |
Following a meeting of the working group on the 10th
August 2012 recommendations were made by the working group which were
accepted and have been incorporated into the final version of the strategy. The Council’s first Environment Strategy was adopted
by Cabinet on the 5th December 2012. |
|
Adoption of the
Doncaster Council Statement of Policy (Gambling Policy 2013) |
Statutory
Plan |
|
Going
to Cabinet 19th December 2012 |
|
|
Performance 2012/13 (Qtr 2) – St Leger |
Continue to
monitor. |
Panel |
Through
quarterly report & review |
To
hold relevant Directors to account. Focus on key areas of overspend &
underperformance and consider actions for improvement. Identify issues for
future consideration. Ensure
concerns identified continue to be monitored. |
|
22nd
January 2013 |
Update
Report
from Mayor Peter Davies and Cllr Cynthia Ransome (TBC) |
To understand
priorities and review progress later in year. During the course of the year
continue to measure aspects through Quarterly Performance reports. |
Panel |
January
2013 meeting and quarterly performance reports |
To
provide accountability for improvement and improve transparency. |
Place Marketing (Enterprising Doncaster) |
|
|
|
|
|
LDF - Sites and Policies DPD |
|
|
|
|
|
18th
March 2013 |
Update Report Cabinet Member
Portfolio Holders |
To understand
priorities and review progress later in year. During the course of the year
continue to measure aspects through Quarterly Performance reports |
Panel |
March
2013 meeting and quarterly performance reports |
To
provide accountability for improvement and improve transparency. |
Performance 2012/13 (Qtr 3)- DMBC |
Continue to
monitor. |
Panel |
Through
quarterly report & review |
To
hold relevant Directors to account. Focus on key areas of overspend &
underperformance and consider actions for improvement. Identify issues for
future consideration. Ensure
concerns identified continue to be monitored. |
|
Performance 2012/13 (Qtr 3) – St Leger |
Councillor
for Edenthorpe, Kirk Sandall
& Barnby Dun
Home Tel:
01302 880242
Email: Tony.Revill@doncaster.gov.uk
24 October
2012
Peter Davies
Mayor of
Doncaster
Floor 1
The Council
House
College Road
Doncaster
DN1 3AJ
Dear Peter
Work, Skills and Enterprise Programme Going Forward and Update on
Opportunity Centres
At the Regeneration and
Environment Overview and Scrutiny Panel meeting held on the 17th October 2012,
the Panel received a report providing a ‘Work, Skills and Enterprise Programme Going Forward and Update on
Opportunity Centres’. The report was outlined to Members of the Panel
which summarised
the current position with regard to the future work and skills support offer
within the Work, Skills and Enterprise Programme (Success Doncaster) and also
provided an update on Opportunity Centres.
Following
the discussion, Members of the Panel agreed on the following recommendations:
1.
That a response be
provided following a Members enquiry made on a budget underspend from the
2011/2012 budget allocated for Outreach Workers and why it was not spent.
2.
That consideration
is given to utilise those volunteers operating within the new library model
more, in order to carry out their role within Opportunity Centres (those
located in Libraries) by providing them available funding and complete
training.
At the Panel meeting, a Member spoke about the experiences of the
Opportunity Centre located within Balby Community
Library where it had been observed that volunteers were making an effort to
service the Opportunity Centre, in the absence of a Customer Service
Adviser. It was felt that volunteers
such as those were in need of further support to undertake this additional role
and that available funding should be looked at further in order to achieve
this.
Page 1
Page 2 (Continued)
The Panel also raised the following comments and concerns: -
·
Action Plan – Members of the Panel were
dissatisfied regarding the lack of progress that had been made taking forwards
most of the recommendations within the Action Plan, some of which are outlined
further below. They were also
disappointed at the length of time it had taken to bring the response to the
scrutiny review that has been undertaken over a year ago to the Panel’s
attention.
·
Use of Budget Underspend – Following a
discussion around a queried budget underspend, a Member proposed that the money
not spent on providing Outreach Workers is spent keeping the stand alone
Opportunity Centres open and that efforts are made to find suitable Outreach
Workers.
·
Outreach Engagement Model – Regarding
the Outreach Service, it was acknowledged that there is a need to link more
effectively with the provision that is already out there. It was recognised that the mobile bus service
is a service that is under used and Members are keen to ensure that actions
will be taken to look into using a second bus that may be available, maximise
the buses potential and ensure that it is promoted and targeted in the most
effective way. Some Members expressed concern that Community Safety Advisers
are unable to engage with who they would like to, in particular those
individuals that are in need of additional support. Some Members questioned the
effectiveness of the busses and asked how many people had found jobs.
·
Opportunity Centre Performance – Concern
was expressed over the figures presented to the Panel which showed a downward
trend in the outputs achieved for people into jobs and those supported into
education and training at some Opportunity Centres. Members felt that these did not reflect how
much the top performing centres had achieved and did not take into account the
reasons behind the centres with the lower performances. The absence of staff
and trained staff, it was felt, was the main contributory factor. Members felt
that there was a lack of attention to what made the better ones perform so well
and questioned why lessons hadn’t been learnt from the stronger centres to
improve the others that weren’t. One
Member believed that the links between the performance of the Opportunity
Centres and outreach work are integral and that perhaps some could be improved
with Outreach Workers. It was reflected
upon that the positive outreach work that was previously undertaken at Denaby Opportunity Centre is why it performed with the
historical highest outputs.
·
Work Programme Providers - There was
concern over the performance of the work programme providers namely A4E, Serco
and Job Centre Plus. Some Members
expressed concern that A4E and Serco had made no appearances at all Opportunity
Centres and Job Centre Plus did not engage with clients and were not present
long enough to provide a suitable level of support to those in need of
assistance in finding work. It was noted by Members that the list of work
programme providers was long and most providers had never been heard of.
Page
2
Page 3 (Continued)
·
Opportunity Centre Staff Training – Members
felt that the training of Opportunity Centre staff to undertake their role was
a key issue that is in need of addressing in order for them to carry out their
role to the best of their ability. Some Members felt that this was a key reason
behind those centres which showed lower performances.
Overall, Members felt that with regard to the future work and skills
support offer, it is about ensuring that those unemployed receive the necessary
support and assistance to get them into employment and recognise that there
needs to be some kind of mechanism which is sustainable and consistent.
Some Members from the Panel expressed the positive merits of Opportunity
Centres and felt that they provided important community engagement but more
importantly, an essential service for supporting people back into work
particular those who are most vulnerable and who are financially deficient and
cannot afford to go to the Job Centre Plus in Doncaster on a daily basis to
look for work.
On behalf of the Panel, I would like to thank Scott
Cardwell, Director of Development and Peter Dale, Director of Regeneration and
Environment for presenting the report and responding to questions. I would also like to thank Julie Grant,
Assistant Director Customer Services & ICT, Julie Wilson, Head of Business,
Commerce & Tourism, Nick Stopforth, Head of
Service for Libraries, Christian Foster, Programmes Manager and Roy Barnes,
Work & Skills Client Manager for attending
the meeting and also answering questions
from members of the Panel. I therefore
look forward to receiving a response from you no later than 26th November 2012 on the
recommendations and comments outlined above.
Kind
regards,
Councillor A Revill
Chair – Regeneration and Environment Overview
and Scrutiny Panel
cc. Jo Miller, Chief Executive
Chair/Vice
Chair of O.S.M.C.
Cabinet
Peter Dale,
Director of Development
Scott Cardwell, Director of Development
Julie Wilson, Head of Business, Commerce
& Tourism
Roy Barnes, Work & Skills Client
Manager
Julie Grant, Assistant Director Customer
Services & ICT
Nick Stopforth, Head of Service for Libraries
PD/JB
26th
November 2012
Councillor
Tony Revill
Chair of
Regeneration and Environment O&S Panel
Scrutiny
Offices
2 Priory
Place
Doncaster
DN1 1BN
Dear Tony
Work, Skills
and Enterprise Programme Going Forward and Update on Opportunity Centres
Thank you for your letter dated 26th October
2012, following the meeting of the Regeneration and Environment Overview and
Scrutiny Panel on 17th October 2012. I have considered the
recommendations and comments raised following the Panel’s discussion of the report ‘Work,
Skills and Enterprise Programme Going Forward and Update on Opportunity
Centres’, and I have the following comments.
With regard
to the first recommendation:
1. That a response be provided following a
Members enquiry made on a budget underspend from the 2011/2012 budget allocated
for Outreach Workers and why it was not spent.
There is no budget assigned in 2013/2014 for work and
skills support for individuals, including continuity of the service in the five
Opportunity Centres, currently funded
through WSEP.
It is my view that any proposed use of the WSEP budget
going forward must take full account of the changing work and skills landscape,
the greatly reduced resources available to the Council, and the need to ensure
a more sustainable and consistent
approach.
I note the agreed minutes from the meeting that ‘members were of the opinion that this
underspend should be rolled over and further discussions to be held’.
The paper presented at the meeting on 17th
October provided information (paragraphs 21, 35 and 36 of the report) on the
budget underspend from the 2011/12 budget allocated for outreach workers, and
why it was not spent. With regard to the Outreach & Engagement proposals,
following a representation, I asked for an investigation of the provision from
an early contract termination. This caused a delay in being able to progress
recruitment. Also, at that point, the City Deal came along with its
developments such as the Skills Deal and the Apprenticeship Hub, which offer opportunities
to deliver skills and job programmes in a different way. There had been a significant passage of
time, and it raised questions over the appropriateness of recruiting the
outreach workers for a limited period.
With regard to the second recommendation:
2.
That
consideration be given to utilise those volunteers operating within the new
library model more, in order to carry out their role within Opportunity Centres
(those located in libraries) by providing them available funding and complete
training.
I am pleased that the Panel recognises the positive
contribution that volunteers are
making to the frontline delivery of community libraries. I agree that the Council should consider how
best to use volunteers, by building on the existing effective practice within
libraries and elsewhere within the Council. This will form part of any future
proposals for the use of limited WSEP funding going forward. With this in mind,
I have asked officers to consider how best this can be achieved.
I note the comments made by Panel members with regard to
the Action Plan. This was produced when more WSEP funding was available and
pre-dated the current work and skills priorities and initiatives, including the
City Deal Apprenticeship Hub and the Work and Skills Partnership. It is my view
that in order to ensure that actions are aligned to agreed priorities going
forward, the Action Plan should be refreshed as part of a wider response to
these wider work and skills priorities for Doncaster and used as reference
point by Council and its key partners. With this in mind, I have asked officers from both the library
service and Success Doncaster to review progress made, and provide updates once
the actions for the WSEP going forward are agreed. I am also considering
further work to develop a ‘Work and Skills Steering Group’, to oversee and
advise on local delivery of work and skills support.
I am pleased that the Panel recognised there is a need to
link more effectively with provision that is already in place to support people
into work and skills. The paper discussed by the Panel on 17th
October identified a number of proposed
actions to build stronger links with relevant
provision and providers going forward. Included within these was a focus on getting more use out of the
Success Doncaster mobile bus service. Planned activity with the mobile bus has
been significantly ramped up - from the 17th October until the
end of March 2013, the bus will be
deployed 20 times across different community locations; 4 of these 20 visits will be targeted specifically at
engaging with local business.
All engagements with individuals and business using the
Success Doncaster bus are logged,
including information on referrals to other provision. Going forward, a sample
of clients using the bus will be followed up, in order to provide some
information to assess progression outcomes.
However, because there are a variety of potential onward referrals, including
to Opportunity Centres, the Work Programme and training or education providers,
these may not all lead to a job outcome over time. It may also not be possible
to access detailed job information relating to specific clients from these
onward referrals, because of having to
comply with data protection requirements. Officers are currently investigating
how best to capture volumes and information relating to job outcomes from
providers. The potential to increase mobile usage and access across Doncaster,
through a second bus owned by North Doncaster Development Trust, is also being
explored.
With regard to performance across the Opportunity
Centres, the report considered by the Panel on 17th October, and
subsequent discussion, confirmed that this varies greatly. While this may be in
part due to factors around staff
resources and training, the performance achieved overall since the Opportunity Centres were set up
is low. Therefore, I am considering further work to identify a more sustainable
delivery model, which makes best use of the very limited WSEP resources
available to the Council, builds on the
best practice (including that identified from the best performing Centres and the use of volunteers in
libraries), provides sufficient training for frontline staff and harnesses the
wider resources available through working with partners.
I note with interest the Panel’s comments with regard to
the Work Programme providers and Jobcentre Plus. It is my understanding that
Jobcentre Plus is very supportive of the Council’s approach to providing easily accessible work and skills support,
evidenced through its membership of Business Doncaster, involvement on the Work
and Skills Partnership Board, and the work in partnership with Opportunity
Centres. This provides the Council with an opportunity to develop these
relationships further.
The resources currently available to the Work Programme
providers, and Jobcentre Plus, to support local residents into work, are much
greater than those of the Council.
However, these resources fall outside of the direct control of the
Council. I agree there is a need to
maximise the use and impact of these external resources for the benefit of
Doncaster. With this in mind, I have asked officers to initiate a dialogue at
strategic level, in order to review existing activity and further develop
stronger operational links.
Reports on the way forward for the WSEP will be
considered by Executive Board and Cabinet during December 2012 and January
2013.
In summary, I would like to thank the members of the
Panel for their time and consideration of these issues.
Yours sincerely
Peter Davies
Mayor of
Doncaster
YOUTH COUNCIL MEETING
6TH DECEMBER, 2012
PRESENT:
17 Youth Councillors
Deborah Burton, Active Involvement
Co-ordinator/Young People's Training Co-ordinator
Linda Hardy, Active Involvement Co-ordinator/Volunteer
Co-ordinator
Councillors Yvonne Woodcock, Doreen
Woodhouse, Alan Jones, Richard Cooper-Holmes and Monty Cuthbert.
Councillor Ros
Jones – Observer
Questions presented to and responses from
the Youth Council are detailed below. At
the conclusion of discussion, the Youth Council requested an update on the
outcome of the review, as this would feed into work on Curriculum for Life
being undertaken by the Youth Parliament.
KEY POINTS RAISED
QUESTIONS TO YOUTH COUNCILORS
Question 1-
What Careers Advice and Guidance do you receive?
Response:
Connexions
go into schools to offer advice, generally at the yearend for years 9 (plus)
and occasionally throughout the year.
Some schools used to have a dedicated connexions office but this has
been removed but replaced with a school careers facility.
Classes
on business studies in industry.
Careers
advice not available in college – only course based.
Question 2. What
is offered to you and how? i.e. school or other mechanisms e.g.
Parents/Carers/website/social media?
Response:
Through
schools, teachers (i.e. form teacher and career teacher) parents, useful
website, Facebook (general), Facebook (Connexions), media, local
newspapers.
The
Youth Council was currently updating its Facebook page and careers advice was
something they would be considering to include.
CVS
– through appointment system.
Make
appointments to see careers officers through Connexions
Question 3. Do you know where to go to if you have questions
about future career?
Response:
Majority Yes.
Yes
– Connexions. Wished for more dedicated
service from Connexions rather than visits every now and then. There was concern that Connexions in town was
closed in the evening when school finished although it was open Saturday
morning until 12noon.
Advised
through school who to approach.
YMCA
– but not the first point of contact.
Some
unaware of information available outside school.
Question 4. Is it enough?
Response:
Mixed
response.
Advice
and information was available but it was also important to note that social
media was an excellent source of information.
It was easy to research yourself but must have the drive to do this.
Question 5. What would you like to be receiving?
Response:
Wished to see more advice offered in
schools and local libraries.
One on one discussions
More work experience
Question 6. How should things be done differently?
Response:
Not enough information outside school.
More
advice and recognition with after school support from teachers and
connexions.
More
personal assistance.
Connexions
offered a texting system with responses being received within 3 days. Some young people thought this was too long a
period, but others thought it was reasonable due to some responses requiring
detailed answers.
Increased
used of information provided through the internet and social media.
Question 7
- Do you feel prepared?
Response:
Mixed response.
Generally
No. Wish for more work experience and
support with the direction that that needs to be taken.
Not enough links to college and businesses.
Not enough support beyond school
Make
sure they have good grades in English and Maths – fear of grades for
university. How much will university
cost?
Biggest gap is students who don’t know what
they want to do.
Need to feel prepared and think ahead –
need life skills – finance – university – work.
Not aware of entitlements.
Work experience
It
was expressed that in some schools it felt like it was not a priority and you
were placed anywhere, rather than somewhere that offered you an insight into
what you were interested in.
Not
all schools offered work experience.
Applications
to places that young people had arranged themselves were not processed quickly
enough and placements were falling through.
Voluntary
work was a good place to gain work experience.
Question 8 How
do you feel about the options that are presented to you? (E.g
Apprenticeships, Vocational Qualifications, University, training etc)
Response:
Offered
information on a number of areas, vocational qualifications, apprenticeships,
university. Too many options with no
personalisation.
Lack
of apprenticeship/vocational courses.
University
is pushed to everyone
Assessed
on projected results and the most appropriate career pathway is presented to
young people.
Needs
to be more personal/tailored different learning styles not catered for.
Question 9. Do
you feel they are favoured in any way, do you feel that more emphasis is given
to one option over another?
Response:
Varied
Too
much emphasis on vocational employment and apprenticeships. Specifics mentioned animal care, child care,
beauty therapists.
More
emphasis is placed on vulnerable students.
Not
informed of the skills required locally or nationally but it is impressed that
English and Maths is essential.
Some
young people were aware of what was required in New Zealand and Australia, egg.
engineers and construction workers.
Questions 10 - Are you dealt with individually? Do you have a Mentor?
Response:
Class,
small group and individual discussions.
Some
individual mentors but very few.
Some
vulnerable students have mentors.
Question 11 - is advice and guidance tailored to your
personal choices or what skills required in by the business community?
Response:
Mixed.
Areas that a young person is interested in,
is researched.
Some say it isn’t worthwhile – provided
with random print outs that do not help.
Question 12 - Do you know what business are looking for (locally or nationally)
Response:
Lack
of understanding what the labour market needs but it was essential to be hard
working, motivated and had experience which young people did not have.
No
sufficient knowledge and were not aware of national skill requirements –
information is sought by own research.
Aware
need workers for construction, pubs, Frenchgate
shops, Morrisons and Amazon.
Academics.
Need English and Maths
Question 13 - Do you feel confident about making the
right decisions about the future?
Response:
Mixed
– maybe.
Most
of the time but there is always fear of the unknown.
Safety
nets provide confidence.
School
pressure to achieve good grades but don’t look at practical life working
skills.
Question 14 - Do you know where to go to get a job?
Response:
Yes
– Internet, newspapers, free ads, job centre.
Question 15 - Do you know what training is available to
you to make sure you are skills ready to be able to take a job?
Response:
Mixed.
Yes – school advise.
Youth Council assists.
Question 16 - Do you know feel prepared to find
appropriate training and employment?
Response
Mixed – with one to one help feel more
prepared.
No – too young.
Additional information
Employment prospects
There
was no clear aspiration as the young people were very aware of the lack of
employment and constant redundancies.
Youth Parliament
Youth
Parliament was in the early stages of investigating Curriculum for life –
preparation for work.
Job Centre
One
young person explained the wish to receive training through the job centre and
to do this had to sign on and attend interviews, as if receiving benefits. Because the young person was unable to attend
meetings at the job centre due to undertaking voluntary work, was removed and
subsequently missed out on training.
Visits from Universities
Some young people had received visits from
universities to explain about the funding system. They did not discuss courses and what the
young people thought was important i.e. Grades required for subjects and how to
succeed in securing a place.
Bullying
Students mentioned that they wished to see
harsher punishments for bullies.
Careers and Guidance Meeting
R&E/SC&YP
Joint Working Group
11th
December 2012, 10am, Mansion House
Attended by: -
Councillors:
-
·
Richard
Cooper-Holmes (Chair) - DMBC (R&E O&S)
·
Yvonne Woodcock - DMBC (R&E O&S)Yvonne Woodcock
·
Doreen Woodhouse -DMBC (SC&YP O&S)
·
Alan Jones - DMBC (SC&YP O&S)
·
Nuala
Fennelly - DMBC (R&E O&S)
·
Monty Cuthbert - DMBC (R&E/SC&YP
O&S)
DMBC Officers
·
Jayne Vose – Head of Service for Learner Engagement
·
Lee Tillman – Policy & Partnerships Officer
·
Pam Bolderson – Head of
Connexions/IAG Lead
·
Deborah Burton – Active
Involvement Co-ordinator/Young People's Training Co-ordinator
·
Linda Hardy – Active Involvement Co-ordinator/Young
People's Training Co-ordinator
·
Caroline Martin – Scrutiny Officer
·
Chris Rothwell – Scrutiny Officer
External
·
Ian
Hanks – External Relations Manager, South Yorkshire District (Job Centre Plus)
·
Phillip Harris – Chief Executive, Doncaster
Chamber
·
Dan Fell – Deputy Chief Executive, Doncaster
Chamber
·
Andrew Best – Partner, HSR Law
·
George Trow –
Principal, Doncaster College
Purpose:
To gather evidence for the following review: -
To understand and
address Careers Advice and Guidance to children and young people within
Doncaster Pre and Post 16
Background Information and Statistical
Evidence
The Panel was
presented with Background Information and the Current Picture. Hand-outs that had been circulated with the
agenda including: -
·
Provision
Mapping Information (16-19 Provision and 19-24 Apprenticeship data).
·
Labour
Market Information (LMI) Survey - Doncaster’s Approach to Skills from 2013-
(Feedback from Work and Skills Board: 30 November 2012)
·
Definition
of Careers Education, Information, Advice and Guidance (CEIAG)
·
Regeneration And Environment Overview And
Scrutiny Update On Work and Skills Partnership
·
Careers Advice and Guidance Presentation
covering
o
CEIAG Landscape (Primary/Secondary/Post 16)
o
Children in Care/Leaving Care
o
Recommendations
o
What else could we do?
o
Future Challenges
Provision Mapping Information (16-19
Provision and 19-24 Apprenticeship data)
·
An
overview was provided of the current situation in terms of Careers, Advice and
Guidance and there was a detailed discussion about the Provision Mapping Information
(outlining where young people go post 16) including the following: -
o Statistical information showing that post 16 the number of young people
classed as NEETS (Not in Education Employment or Training) was 6% for post 16
and 2.8% not known.
o That in Doncaster there approximately
62% who are in the sixth form, this is almost double of those not in the sixth
form post 16 due to the high number of sixth forms in place. It was commented that there needs to be a valid
alternative for those young people for whom the sixth form is not a valid
option. It was later commented that some
young people are making the right choices after 16 but that there are others
who are not and have to go back and begin again after 17. Concern was raised about the Governments plans to increase the participation age to which all young
people in England must continue in education or training (requiring them to
continue until the end of the academic year in which they turn 17 from 2013 and
until their 18th birthday from 2015).
o
That
young people are travelling outside of the Borough, although it was
acknowledged that individuals will naturally go to the closest location to
where they live such as which college they choose to go to. For example, Don
Valley is approximately one mile outside of a DN postcode and therefore shows
Doncaster residents going outside of the Borough to continue their education
although it is likely because it is the nearest.
o
Regarding
the table on Page 8 presenting the Further Education Provision Mix for Resident
Learning Aims data, it was commented by one Member that the figures may be
indicative of how much effort schools are preparing young people in the pre-16
age groups.
o
The
table on Page 10 outlining a Combined Provision Mix was discussed and Members
requested a breakdown of the subjects under ‘Not Applicable’ as it showed a
high number
Action:
Breakdown to be provided under ‘Not Applicable’ classification.
Labour Market Information (LMI) Survey
- Doncaster’s Approach to Skills from 2013- (Feedback from Work and Skills
Board: 30 November 2012)
·
A
recap of the Work and Skills Board was provided and Members were informed that
the Board was set up earlier in 2012 and was about bringing together a greater
understanding of the current issues and work towards breaking down
barriers. Part of work has involved
talking and working with employers and stakeholders to identify what their
needs are in the current economy in terms of skills and employment.
·
Work
has also included working on a framework and the purchase and implementation of
a portal to provide better access for pre 16 age groups for careers, advice and
guidance.
·
The
Labour Market Information survey results were presented to the group and
Members were informed that out of 6,000 businesses contacted 613 (13%)
completed the survey. The information
presented to the group showed which areas/subjects the local economy are
looking for from potential candidates.
The following observations and comments included: -
o In terms of high end skills, the
numbers of individuals in Doncaster who have an engineering background were
questioned as some Members felt that the skills levels for this sector were
still available.
o That Doncaster only has a low number
of its own graduates and many leave Doncaster to train and look for employment
outside of the Borough. It was
acknowledged that local opportunities for graduates are low.
o It was also noted that many graduates
who move away from Doncaster do not stay or return as they do not find
Doncaster an attractive place to live.
o It was recognised that it is very
difficult in current climate to find work and that it was a very competitive
and set against the backdrop of benefit changes.
o There was a brief discussion on
apprenticeships and there were a number of views expressed. Observations were raised on whether the issue
of apprenticeships was merely the current ‘vogue’. From a private sector let point of view, it
was noted that for a business, an apprentice will not ‘hit the ground running’
and it was commented that a business may benefit more from a higher level
skilled graduate who will also gain more work experience. It was also noted that apprenticeships
generally engage more with younger people and offer a financial incentive.
o It was noted that we need to think
about what Doncaster economy looks like.
o Regarding the labour market, the group
was informed that although there is the perception that there are no jobs, this
is not necessarily the case. In terms of
the Doncaster labour market, it was outlined that it is heavily influenced by
many agency jobs but that those jobs although temporary could lead to permanent
employment and enable individuals to gain more work experience and therefore be
more marketable.
Youth Council Meeting Feedback
At the
meeting information was provided in relation to the questions and responses
from the Youth Council which are detailed below. It was also noted that the Youth Council
requested an update on the outcome of the review, as this would feed into work
on Curriculum for Life being undertaken by the Youth Parliament.
The following
key points from the information provide and meeting included: -
·
Advised where to go to through school;
·
All young people know to approach Connexions
for careers advice and guidance – on numerous levels e.g. Groups, individual
and class based;
·
Social media is an excellent source of
information but young people need the drive to use this mechanism;
·
Wish to see more information offered at
schools and libraries;
·
Would like more one to one discussions;
·
Too much general information, needs something
more personalised;
·
Not enough support when go to college;
·
Generally young people did not feel prepared
for work and wished for more work experience, but in the current climate this
was difficult, even voluntary work;
·
Felt biggest gap was students did not know
what they wanted to do when they left school, so were unable to prepare
themselves;
·
Instilled that they must achieve good English
and Maths GCSE grades. School pressure
to achieve good grades but do not look at practical life working skills;
·
Lack of understanding what the labour market
needs but it was essential to be hard working, motivated and had experience;
·
No sufficient knowledge and were not aware of
national skill requirements – information is sought by own research;
·
University is pushed to everyone with not
enough vocational/apprenticeship opportunities;
·
Lot
of emphasis on vulnerable students;
Comments
from Members included: -
o It was agreed that the views of the
Youth Council mirrored those of the business community and that it was the
section in the middle that caused a problem.
o It was noted that post 16, young
people know where they are going but when it is post 19 that they found it
difficult to decide what happens next and only appeared to know about the Job
Centre Plus at this point.
o Regarding apprenticeships, it was
commented that these did not necessarily lead to jobs.
o A Member commented that the skills
young people will gain are most likely to be the ones that they will have
during their life.
o It was also commented that sometimes
the brightest children were those that received the least help.
During the
meeting the following comments were also raised and have been categorised for
ease.
Not in Education or Employment and
Training (NEETS)
·
It
was acknowledged that in respect of NEETS (Not in Education or Employment)
significant steps had been undertaken.
·
In
respect of the age group 19-24 year olds who are classified as NEETS there are
actually a number of these who have Level 3 Education and waiting for employment.
Young People
·
It
was noted that it was not always about the young person’s own decision and that
on occasion they are influenced by another person such as a family member or
teacher etc.
·
It
was commented that those young people who are not academic do not necessarily
know what they want, how to get there and also feel that there is nothing out
there for them.
·
It
was also felt that Young People are not quite as realistic as they should be
about the opportunities out there.
Schools
·
It
was commented that it is important to get the messages into schools at a very
early stage.
·
A
Member raised concern that there are disaffected children who are never going
to achieve GCSEs and also those that will go from school to ‘A ‘Levels and then
to University but have no idea about what to do or what is needed.
·
Concern
was also expressed about those responsible for providing the necessary guidance
and advice to young people in schools and felt that teachers were in need of
more life experience in order to carry out this role, it was also questioned
whether Teachers should be undertaking that role at all.
·
It
was observed that young people are not aware of whom the major businesses are
in Doncaster and what they have to offer and some Members felt that businesses
needed to start going into schools.
·
One Member questioned the utilisation and benefit of Personal, social, health and
economic (PSHE) education
in schools.
·
It
was noted that schools were being more reactive and also don’t have the
resources in place.
·
A
Member expressed concern that as a local authority we were unable to provide
the link with schools and employments.
·
The
potential role of parents was referred to and it was commented that they were
an untapped resource that would be of no cost.
Children’s University
·
There
was a conversation about Children’s University and an explanation was provided
to Members about what they are and what they entailed. It was outlined that it had been running for
6 years although more had accessed it in the last few years, that of 500
primary schools, 13 engage with the scheme and that although secondary schools
are invited to participate, none have chosen to so. Members of the working group commented that
they had not been made aware of this provision, asked why Councillors aren’t
involved and asked for further information to be circulated. It was explained that it had been reported in
the press and that Officers and some Members had been involved or made aware.
·
It
was suggested that it could go through the Governors Support function and get
it into the leadership newsletter.
Action: To
obtain further information on Children’s University’s that could be circulated
to Members.
Post 17
·
It
was suggested that perhaps more thought should be given to the changes that
occur educationally Post 17 for those who have made decisions made at 16 plus
which not worked out.
·
Reference
was again made to the concerns about raising the participation age.
Pilot Scheme – Placements
·
The
group was informed about an exercise that had taken place where 60 students had
gone through a reality based selection proves which had resulted in 3 ‘mini
internships’ where all had resulted in positive feedback and 1 had a potential
job. Concern was raised by some Members
about the 57 students who were not successful in gaining a place and were
informed that the idea had come out of the private sector and that businesses
were getting more disappointed with the quality of the young people being
placed on work experience. It was noted
that perhaps the experience for those 57 students not chosen could be used in a
positive way for example, being about the selection process and that jobs are not readily available in the real
world and that employers benefited from having a young person that was more
suitable and ready for the placement.
Our Role as a Local Authority
·
It
was noted that as a local authority, we have a strategic leadership
responsibility and need to use the powers that we have in place as there is no
provision in place
·
It
was believed that there are lots of people working in silos and need to start
communicating more effectively to become more aware of what one another is
doing.
Doncaster College
An outline
was provided on the work of Doncaster College and some highlights included: -
·
That
Doncaster College was a good college that has been operating financially for
the last 2 years.
·
That
there is a special team for Looked After Children.
·
It
should be recognised that some will end up leaving the area.
·
It
was felt that there should be skills/employment base within Doncaster.
Job Centre Plus
The following
comments were made by Ian Hanks of Job Centre Plus
·
The
group was informed that Job Centre Plus does play a role although they don’t
offer guidance they do signpost where needed.
·
There
are a handful of young people who are seeking Job Seekers Allowance at the ages
of 16/17 through hardship.
·
It
was outlined that for the 18-24 age range that this group is more difficult as
there are remote packages made available through youth contracts.
·
Regarding
jobs, it was acknowledged that there are individuals who will avoid it but the
vast majority do want to work and it’s about how they can be helped.
·
From
October 2012 due to new conditionally and sanctions regime there are
individuals who will want to avoid losing benefits.
·
They
also invite partnership organisations in to work with as it’s recognised that
they cannot work alone.
·
That
their focus is about getting people off the register and focus more on
individuals getting a job rather than establishing a career.
·
Some
of the areas that they are involved in include young people - interventions,
group sessions, apprenticeship schemes, CV preparation, and basic interview
techniques and are currently developing group sessions for 50+.
·
It
was also noted that they are unable to go into schools (although can be done
with prior appointment)
Other Challenges
·
That
young people are going to be receiving objective information, advice and
guidance
·
That
positive steps are taken to establish the right mechanism and creating a
framework to achieving a quality offer from having such an ad-hoc process in
place.
·
To
think about what can be achieved through no additional costs.
·
A
Member emphasised that it was important to get the mechanism right and get
expert advice to young people through other avenues such as charity
organisations and Youth Clubs.
·
It
was commented that in respect of what schools are providing heads are placing a
cost on what they can provide. It was
suggested that perhaps Governors should be questioned whether this is
sufficient for young people.
Future Work
·
That
meetings are taking place with schools to identify what exactly they are
providing.
·
That
further work is being undertaken to look at employer led approaches and that
discussions are being undertaken about what the framework may look like. Andrew
Best, HSR Law as a representative of the Work and Skills Board will be meeting
with businesses to gather a business perspective and establish how we can work
together.
·
Regarding
the way forward, it was suggested that there should be an entitlement through
all providers and schools such as Barnsley.
Next Steps
After further
discussion with the working group following the meeting, it was decided that
there needs to be a further meeting with representation from schools, further
information on the role of Governors, feedback from the Private Sector meeting
and more information on the Barnsley model.
Action
Points from Enterprising Doncaster Board Meeting 29th October 2012
Attendees:
Jon Whiteley (Lead: Economic
Linkages) Chair
Malcolm
Cowing
(Lead: Common Economic Factors) Vice Chair
Jim Wren (Housing Champion)
Nigel Brewster
(Work and Skills Champion)
Peter Davies
(Economic Portfolio Holder/Mayor)
Scott Cardwell
(Assistant Director for Development)
Emma Butler
(Economic Policy Officer)
Apologies:
Tracy Harwood (Interim Assistant Director Strategic Housing)
Peter Dale (Director
for Development)
Jo Miller (Chief
Executive, DMBC)
Barbra Hoyland (Portfolio Holder, Housing)
Previous
Actions
No previous
actions were discussed following the restructure and refocusing of work.
New Actions
Action |
Agenda
Item |
Detail |
Lead |
Action By |
1 |
Agenda Item 1 – Welcome,
Apologies and Introductions |
Apologies
noted. |
Jon Whiteley |
NA |
2 |
Agenda Item 2 – Enterprising
Doncaster’s Role |
2a)
Agreement of revised Structure: Structure is formally agreed and signed off. 2b) City
Region Governance As part of
the City deal the SCR LEP needs to look at establishing appropriate
governance arrangements. The
Manchester Model of a combined authority is one that central government has
welcomed and this the model the region will be working towards. There will
be no decision made locally to Doncaster until after the Mayoral election in
May 2013. It is expected to be taken
to parliament November 2014. The LEP Board will be receiving a paper
outlining the proposals on the 20th November. |
Jon Whiteley Nigel
Brewster |
NA |
3 |
Agenda Item 3 – Doncaster’s
Key Challenges |
A
presentation was given providing the headlines from the refreshed Local
Economic Assessment. Feedback
from the stock take event which took place on the 4th October 2012
was also given. Key focus for the
wider partnership will be: 1. Whole
partnership one team working plus approach/ 2. Getting
Young People into work. 3.Promoting
the Borough. 4. Science
of Behaviour. 5.
Engaging with Schools. Questions
and points raised that need further consideration are: * The
impact of the Scottish independent vote on the Carbon Capture Power Park. * What
does the future economy look like? Ten
years ago Doncaster believed that the majority of jobs would be within the
aviation industry…can we make an accurate prediction as to where jobs will be
or do we need to be upfront that we don’t know? * Digital
connection needs to be included within the pipeline map. |
|
|
4 |
Agenda Item 4 – Current
Champion Activity |
4a) An
update was provided on the three areas: *
Logistics * Business
Growth * Visitor
Economy. Action: By
exception further to briefing paper there was an additional item discussed
about the Logistics Group becoming the sector group for the LEP. The group discussed this at length and felt
that the benefits and risks needed to be outlined before making any decision
as well as Doncaster’s “asks” of the LEP.
Action: It was
asked that the Mayor was fully briefed on the progress of the logistics group
regularly. 4b) Work
and Skills An update
was provided on the interim results of the Labour Market Information
assessment. The
results mean that the partnership will need to relook at its current
focus. The results are to be discussed
at the November meeting. An action
plan will be developed and tabled at the next Enterprising Doncaster Board. Action: Revised
Action Plan of the Work and Skill Board to be submitted for discussion at the
next Enterprising Doncaster Board. 4c)
Housing A briefing
was tabled. The Local
Development Framework (LDF) Core Strategy is now adopted. Currently consultation is being undertaken
for the Sites and Policies. This will
go through the process and aim to be in Examination In Public in November
2013. Key
challenge for the housing market is build numbers. Government initiatives that have been put
in place to elevate the issue are all short term fixes. Medium term we need
to be looking at creative and flexible ways of working that result in fast
action. The Autumn Statement should
provide additional assistance. Marketing
Doncaster appropriately will have a positive impact on the housing market. Finance is
obviously critical to the housing market but a lot of banks continue to be
cautious with the Yorkshire Bank withdrawing 100% from the property
market. The New Start offer is also
been approached cautiously and not releasing the amount of mortgages
anticipated. |
Jon Whiteley |
|
5 |
Agenda Item 5 – Economic
Portfolio Holder Update |
North
Bridge is due to be opened to outgoing traffic this week. A piece of
work has been commissioned to look at the development of the North of
Doncaster and opportunities. A group
has been set up from all localities down the East Coast Main Line to protect
and promote the line. Currently is
includes all local authorities but is set to expand to include businesses and
tourism. Action: Businesses
should be asked how infrastructure could be improved to support them. To be raised at Business Doncaster. |
|
|
6 |
Agenda Item 6 – Business
Doncaster Offer |
The paper
outlining the offer of Business Doncaster was tabled. It was formally adopted by Enterprising
Doncaster. Concerns
were raised that partners were not all using the brand. Action: Set a date
where all branding will switch from individual brands to Business
Doncaster. Supporting this clear
guidance needs to be provided as to what this means. Action: Peter
Davies to raise branding with the Chamber at his next briefing with them. Action: Jon Whiteley to explore with Ian Hanks what role JCP will
play in Business Doncaster. |
|
|
7 |
Agenda Item 7– Place
Marketing |
It was
agreed that Enterprising Doncaster would put itself forward to lead on place
marketing on behalf of Doncaster Together.
This was
supported by the Mayor. Action: Jon Whiteley to put this proposal to Jo Miller on the 30th
October. |
|
|
8 |
Agenda Item 8 – Champion
Updates by exception |
Non
Raised. |
|
|
9 |
AOB |
Future
meeting dates to be circulated. |
All |
|
Regeneration & Environment Overview and
Scrutiny Panel
Performance Information –
2012/2013 Quarter 2
Briefing Note
EXECUTIVE
SUMMARY
1.
This
report presents the Regeneration & Environment Directorate financial and
performance information for quarter 2 of this financial year 2012/13.
2.
The
Directorate is projecting an underspend of £266k, this is an improvement on the
Q1 projection of a £316k overspend. .
3.
The
forecast Capital spend for 2012/13 is £125.63m, a decrease of £1.38m from the
Quarter 1 estimate. This is mainly due
to the re-profiling to 2013/14 of a number of schemes. The White Rose Way and CCQ Schemes are
progressing well and the FARRRS expenditure profile will be revised due to the
delay in starting phase 2 works.
4.
Progress against Corporate Plan objectives has
continued the positive trend of the previous quarter.
5.
Further
details on the projected year-end position for revenue and capital and
performance progress against the Council’s Corporate Plan objectives are provided
in the remainder of this report and in Appendix A
FINANCIAL
POSITION
Revenue
6.
The
revenue budgets in Regeneration & Environment are projected to underspend
by £266k; this is after £689k of recurrent underspends in specific areas being
transferred to CYPS. The main
underspends are Environment £351k, Development £194k and Trading & Support
Services £86k with the main overspend on Strategic Housing £331k. The trading accounts are projected to
underachieve their budgeted surpluses by £40k mainly due to overspends on Metroclean £392k, coupled with underspends on Markets £224k
and Public Building Maintenance generating additional income of £171k.
7.
A
summary of the variances for quarter 2 for 2012/13 for the Regeneration & Environment
Directorate are provided below, further detail on all the variances is provided
in Appendix A.
|
Gross Budget £m |
Net Budget £m |
Year-end Variance £m |
Variance as a % of Gross
Budget |
Regeneration & Environment |
79.16 |
46.44 |
-0.26 |
-0.3% |
8.
Other
significant variances are outlined below:
Significant
variances at quarter 2 |
£m |
Underspends: |
|
Waste and Recycling
- Includes collection underspend of £168k, partly due to reduction in
contractor's costs as a result of the Sterecycle
closure & disposal underspend of £321k due to reduced tonnage and the
alternative provider being cheaper than the Sterecycle
contract. |
-0.57 |
9.
Virements
are set out for approval per the financial procedure rules. The following virement
is included in the position presented and are subject Cabinet approval:
|
Description |
Directorate |
£m |
1 |
CAPITAL
- Movement of projects within parks from R&E to A&C Capital Programme
to reflect project lead by Area Managers. |
R & E (Capital) |
0.99 |
|
A & C (Capital) |
-0.99 |
Housing
Revenue Account
10.
The Housing Revenue Account
(HRA) budget changes at quarter 2 reflect the use of £1.8m to support the delivery of the capital
programme for example the delivery of heating conversion and six streets
refurbishment. There have been further savings on
borrowing and on management fees, offset
by an increase of £0.3m in bad debt provision resulting in an estimated surplus
of £2m for 2012/13. The major variances
are due to £1.9m on the management fee reduction, £1.9m on savings against
borrowing at lower interest rates.
11.
This
in year surplus of £2m less the appropriation of £1.8m to support the capital
programme will increase the HRA balance from £6.7m as at 1st April
2012 to £6.9m as at 31st March 2013.
Capital
12.
A
summary of the Capital Programme outturn position for the Regeneration &
Environment Directorate is below and further detail is included in Appendix A.
13.
Directorate |
2012/13
Revised Base Budget |
2012/13
Revised Estimates Qtr 1 |
2012/13
Revised Estimates Qtr 2 |
2012/13
Actual Spend to 30/09/12 |
Variance
Quarter 2 from Quarter 1 |
|
£m |
£m |
£m |
£m |
£m |
Regeneration
& Environment |
129.99 |
127.01 |
125.63 |
30.93 |
-1.38 |
14.
The
estimated outturn figure
for the 2012/13 Capital Programme is £125.63m and capital projects, are in the main,
delivering as planned. Actual capital spend was £30.93m at 30th
September 2012 and is approximately a third of the estimated outturn figure.
This is normal at this point of the financial year and it is expected that
expenditure will increase in line with estimated profiles at Quarters 3 and 4,
as projects progress/complete. Scheme updates at Quarter 2 are:
·
White
Rose Way – Phase 1 and 2 of the scheme are making good progress and is on
schedule for completion;
·
FARRRS
- A contractor has been selected and initial works have been completed.
The current profiled expenditure will need significant revision following
delays to the start of Phase 2 of the contract;
·
CCQ
- The projects are progressing largely in line with projections and the move to
the new Civic Office will start in 19th November and be completed in
February 2013;
·
Waste
PFI –The Council, together with Barnsley and Rotherham Councils, has entered
into a twenty five year contract with 3SE to dispose of the Councils’ residual
waste. Construction is scheduled to
commence in January 2013 with the facility due to be operational in July 2015.
·
Mercury
Abatement £1.50m – the original project for the installation of mercury
abatement equipment and three new cremators has reached practical completion at
lower than budgeted cost, additional access and canopy works £0.21m have been
undertaken from the remaining funds.
PERFORMANCE
15.
Progress against our Corporate Plan objectives has continued the positive
trend of the previous quarter. The
Regeneration and Environment Directorate has 15 priorities spread across 4
themes. Thirteen of these priorities are
on track and the remaining two are mostly on track but with some concerns,
which if not addressed could affect delivery This represents very positive
performance for the Directorate.
16.
There has been a good improvement in the jobs
created through the work of the Success Doncaster and Invest in Doncaster
teams. This PI, although below was target in Quarter 1, is now above target.
The outturn for Overall Investments Gained has far exceeded expectation and we
have almost achieved our annual target. We expect investments to grow further
in Q3.
17.
We are also ahead of a number of targets in Housing:
- we are well on target for the completion of Neighbourhood Investment Plans;
and we have secured £26.4m of ‘External Investment’ for housing priorities against
the 2011-2014 target of £30m. The funding secured is from the 2011-15 HCA
framework and although over-achieving our targets so far, there is no more
money available outside of this framework, so the 3-year target of £30m should
remain unchanged.
18.
We have stretched our target, from 60% to 80%, for the Percentage of fly-tipping incidents that are investigated by the Council
and are ahead of this target with 88% of reported incidents having been
investigated.
19.
However, there is a recognition that we have to
improve on performance in the following areas:
·
PDRs – The Directorate has missed the target for PDR
completions in Q1 and Q2. Assistant Directors are following this up with Heads
of Service as a matter of urgency and we
expect to address the shortfall early in Q3;
·
Implementation of Critical and Major
Audit Actions – The directorate has not been able to report
on progress against a number of major and critical actions relating to Journey
Time on Key Congestion Routes. The team that report on this is the team
that is working on the FARRRS project so, FARRRS work taking priority and
therefore have not been able to report on the audit actions. However, as this
is now no longer a national performance indicator, the need for this
information and subsequent commitment of resources to collect and analyse this
data is currently under review by Internal Audit;
·
Sickness – at 11.18 days our sickness is
slightly off the target of 10.09 days but is an improvement of our 2011-12
sickness figure of 13.86 days. Reducing sickness absence remains a high
priority for the directorate and, in line with corporate guidance, there is a
continued focus on areas of concern including data quality; compliance with the
Council's policy; and are continuing work with HR to improve effective
monitoring and management of staff in those areas with the highest absence
rates.
·
Category 1 Hazards resolved in 6
months - remains
below target but a Systems Thinking Review and work with the service has helped
to improve working practices. This, along
with an increase in resources across the team, has resulted in an improved
performance in Q2.
·
Empty Properties – although the number of empty
properties is currently on a downward trend and the Council programmes to bring
properties back into use have been recognised by the HCA as best practise, the
number remains high and more work is needed in this area.
Report Author & Contributors
Alan Lowther, Corporate Policy &
Performance Manager
Tel: 01302 737647, E-mail: Alan.Lowther@doncaster.gov.uk
Peter Dale
Director of Regeneration &
Environment
Understanding the Quarter 2 Performance Report
Symbols are used within this report to give a
visual representation of performance.
These symbols, and what they represent, are detailed below.
Status
Status gives and overall rating for the
objective taking into account the progress against activity, performance
indicators and mitigating risks
|
|
|
Corporate Objective on track with minimal, if any, concern about
delivery |
Corporate Objective mostly on track but some concerns that if not
addressed could affect delivery |
Corporate Objective currently off track with significant concerns
about delivery |
Milestones
This shows what progress has been made against
the delivery dates for milestones linked to the objective and is demonstrated
with the following symbols
|
|
|
Progressing and on track |
Check progress on milestone dates |
Milestone dates have been missed |
Performance Indicators
Performance indicators (PI) have been
structured on Covalent with red, amber and green thresholds being personalised
for each PI
Performance |
Finance |
|
|
OK –
Performance on target – denotes current value is between the amber/green
threshold and the best value If
the data value is equal to the amber threshold, and the amber threshold is
equal to the target, the PI status will be green |
Under-spent
or on budget |
|
Warning –
Performance below target – denotes current value is between the amber/red
threshold and the amber/green threshold If
the data value is equal to the amber threshold, and the amber threshold is
not equal to the target, the PI status will be amber |
Overspend
is less than £250k |
|
Alert –
Performance significantly below target – denotes current value is between the
amber/red threshold and the worst value If
the data value is equal to the red threshold, the PI status will be red. |
Overspend
exceeds £250k |
Risk Profiles
Risks are profiled in line with the Corporate
Risk Management Framework and the risk profile score determines the overall
status.
|
|
|
Low level risks with a profile score between 1 and 4 |
Medium level risks with a profile score between 5 and 19 |
High level risks with a profile score between 20 and 25 |
Direction of Travel
The direction of travel looks at whether
things have improved stayed the same or become worse when we compare
performance with data reported in the previous quarter
↑ |
↔ |
↓ |
Getting better |
Exactly the same as previously |
Getting worse |
1. Regeneration & Environment Performance Profile
Objective Status |
PI Profile |
Risk Profile |
|||||||||||||||||||||||||||||||||||||||||||||
|
|
|
Direction
of travel |
Status |
Corporate Plan Objective |
Milestones |
PIs |
Data Only |
Risks |
|||||
↔ |
|
Creating the conditions for Economic Engagement |
|
|
|
|
2 |
|
1 |
|
|
↔ |
|
Promoting Economic Engagement |
|
|
|
|
|
4 |
1 |
|
|
↔ |
|
Supporting strong partnerships |
|
|
|
|
|
1 |
3 |
|
|
↔ |
|
Increasing inward investment |
|
2 |
|
|
|
1 |
3 |
|
|
↔ |
|
Promotion of our key cultural assets |
|
1 |
|
|
|
No risks |
|||
↔ |
|
Engage with the private sector to ensure business
influences improvements to the economy |
|
|
|
|
|
2 |
|
|
|
↔ |
|
Seek to rebalance the priority given to public transport
over other modes by making greater use of road space currently being used
solely for buses |
|
|
|
|
|
2 |
|
|
|
↓ |
|
Achieve Better Quality Homes by improving housing
standards in Doncaster |
… |
1 |
|
1 |
|
|
2 |
|
|
↓ |
|
Achieve Better Places to live by increasing supply &
affordability of housing & promoting housing investment in Doncaster |
|
4 |
|
|
|
1 |
2 |
|
|
↔ |
|
Achieve Better Housing Choices for People by taking into
account the housing implications in the Localism Act and by contributing to
corporate work to improve universal services/life chances |
|
1 |
|
|
|
2 |
|
|
|
↔ |
|
Deliver a stakeholder-engaged VFM service by supporting
the SCR Housing & Regeneration Board & responding to any legacy
recommendations arising from the ceasing of the Housing Improving Board |
|
2 |
|
|
|
|
2 |
|
|
↔ |
|
Effectively enforce against environmental offences
(including noise nuisance, littering & fly tipping) |
|
2 |
1 |
|
|
|
1 |
|
|
↔ |
|
Effectively progress the Barnsley, Doncaster and
Rotherham (BDR) waste PFI project |
|
|
|
|
|
|
3 |
|
|
↔ |
|
Implementation of the Local Development Framework |
|
|
|
|
|
2 |
3 |
|
|
↔ |
|
Implement Doncaster's Environment Strategy |
|
|
|
|
|
|
2 |
|
|
… |
… |
Housing Improvement Plan |
… |
… |
… |
… |
… |
… |
… |
… |
|
Governance Indicators
Days lost due to sickness |
Implementation of Critical and Major Audit Actions |
Performance Development Reviews |
|
1 out of 6 achieved |
|
Regeneration and Environment Revenue Report |
||||
|
|
Gross Budget (£k) |
Net Budget (£k) |
Variance |
|
|
|
|
|
|
Regeneration & Environment Total Revenue Variance |
79,160 |
46,438 |
-264 |
The revenue budgets in Regeneration & Environment are
projected to underspend by £266k; this is after £689k of recurrent
underspends in specific areas being transferred to CYPS. The main underspends are Environment £351k
(including a £571k underspend on Waste and Recycling, which may increase once
the tonnage trend has been established), Development £194k and Trading &
Support Services £86k with the main overspend on Strategic Housing
£331k. The trading accounts are
projected to underachieve their budgeted surpluses by £40k mainly due to
overspends on Metroclean £392k, coupled with
underspends on Markets £224k and Public Building Maintenance generating
additional income of £171k. |
Individual service
budgets with a red profile
|
|
|
|
|
|
Strategic Housing Revenue Variance |
3,210 |
2,050 |
331 |
Strategic Housing still projected
to overspend following realignment of budgets. Further action will be taken to improve
this position coupled with Housing Strategy review undertaken by Chartered
Institute of Housing. |
Regeneration and Environment Capital Report |
|
||||
|
|
Revised Base Budget |
Quarter 1 Forecast |
Quarter 2 Forecast |
Actuals to date |
|
|
|
|
|
|
|
Development |
67.81 |
63.05 |
64.45 |
17.50 |
FARRRS - the current profiled
expenditure will need significant revision following delays to the start of
Phase 2 of the contract. White Rose Way - progressing well
but there is a risk that the trigger point for £0.4m S106 funding due from
the Homes & Communities Agency (HCA) may not be reached or will be too
late for use on this project. Any
shortfall can be funded from the Council's LTP allocation but further plans
for those monies must take account of this potential commitment. CCQ programme - progressing as
expected and does not raise concerns at Quarter 2. Main areas of spend include CCQ
works £21.0m, FARRRS £24.2m and White Rose Way £14.3m. The increase of £1.4m is mainly from White
Rose Way due to a combination of increased costs from delays in the bridge
installation (covered by additional grant) and bringing forward expenditure
to take advantage of new flexibilities in DfT
funding. |
|
|
|
|
|
|
|
|||||
|
Transport |
7.20 |
6.77 |
7.00 |
1.03 |
|
|||||
No significant issues for this
area of the programme at Quarter 2.
Main spend includes Integrated Transport Block £2.4m, Highways £3.0m
and Other Maintenance £1.4m. |
|
||||||||||
|
Other Environment Schemes |
3.89 |
3.86 |
1.27 |
0.03 |
||||||
No significant issues for this
area of the programme at Quarter 2.
Main spend includes Interim and Long Term Waste Processing £0.7m; the
decrease is mainly due to the virement of £1.0m
Parks and Playgrounds to Adults & Communities Capital Programme and the
re-profiling of £0.9m Waste related projects to 2013/14. |
|||||||||||
|
Total Environment |
11.10 |
10.63 |
8.26 |
1.06 |
||||||
No significant issues for this
area of the programme at Quarter 2. |
|||||||||||
|
|
|
|
|
|
|
|
||||
|
Housing General Fund |
6.20 |
8.42 |
8.54 |
0.46 |
No significant issues for this area of the programme at
Quarter 2. Main areas of expected spend are Empty Property Strategy £3.2m,
Achieving Access and Inclusion £2.3m, Windhill
Efficiency works £1.2m and Six Streets £1.0m. |
|
|
|
|
|
|
|
Housing Revenue Account |
42.51 |
41.97 |
41.73 |
11.22 |
No significant issues for this area of the programme at
Quarter 2. Decent Homes Programme
decline rate increased resulting in reduced profiled spend. New contractor being progressed & it is
anticipated to be agreed before year end.
Position being monitored, will be updated in Q3. Main areas of spend include Decency Works
£27.5m, Planned Improvements £7.4m and Affordable Housing £2.1m. Decent Homes government funding for 13/14
£7.4m has been confirmed. |
|
|
|
|
|
|
||||
|
|
|
|
|
|
||||
|
|
|
|
|
|
||||
|
Total
Strategic Housing |
48.71 |
50.39 |
50.27 |
11.68 |
||||
No significant issues for this area of the programme at
Quarter 2. |
|||||||||
|
|
|
|
|
|
|
Trading
& Support Services |
2.16 |
2.39 |
2.13 |
0.64 |
No significant issues for this area of the programme at
Quarter 2. Main area of spend is
Mercury Abatement works £1.0m. |
|
|
|
|
|
|
|
Revenue Costs of Capital |
0.23 |
0.56 |
0.52 |
0.05 |
No significant issues for this area of the programme at
Quarter 2. Main areas of spend are CCQ
decant and aerial relocation £0.2m and Transport related costs £0.3m. |
|
|
|
|
|
|
|
Regeneration
& Environment Total |
129.99 |
127.01 |
125.63 |
30.93 |
There is a risk attached for an element of the WRW
funding. Aside from these, there are
no significant issues for this area of the programme at Quarter 2. |
Director’s Comment Progress against our Corporate Plan
objectives has continued the positive trend of the previous quarter. The Regeneration and Environment
Directorate has 15 priorities spread across 4 themes. Thirteen of these priorities are on track and
the remaining two are mostly on track but with some concerns, which if not
addressed could affect delivery. This
represents very positive performance for the Directorate. I am particularly pleased with the
improvement in the jobs created through the work of the Success Doncaster and
Invest in Doncaster teams. This PI, although below was target in Quarter 1,
is now above target. The outturn for Overall Investments Gained has far
exceeded expectation and we have almost achieved our annual target. We expect
investments to grow further in Q3. We are also ahead of a number of targets
in Housing: - we are well on target for the completion of Neighbourhood
Investment Plans; and we have secured the amount £26.4m of ‘External
Investment’ for housing priorities against the 2011-2014 target of £30m. The
funding secured is from the 2011-15 HCA framework and although over-achieving
our targets so far, there is no more money available outside of this
framework, so the 3-year target of £30m should remain unchanged. We have stretched our target, from 60% to
80%, for the Percentage of
fly-tipping incidents that are investigated by the Council and are ahead of
this target with 88% of reported incidents having been investigated. However, I recognise that we have to
improve on performance in the following areas:
|